Innovation is required to facilitate the rapid rollout of non-synchronous generation and prevent grid balancing and stability challenges. Without new solutions, onshore grids will become weaker, which will lead to issues in system operation. These issues include:
- Increased likelihood of instability events;
- Increased need for imported electricity;
- Maintaining reliance on synchronous fossil fuel generators on stand-by.
Preliminary work conducted within the Offshore Wind Accelerator, identified an opportunity to enable offshore wind farms to play a role in stabilising the onshore network using innovative technologies.
The INCENTIVE project was set up to build on this opportunity. Competitively awarded funding from Ofgem’s Strategic Innovation Fund, the project is investigating how the electrical grid can be strengthened by installing innovative energy storage and converter technologies at the point of onshore grid connection.
To build commercial confidence in the technologies, the project has three phases. The Discovery Phase was successfully conducted in early 2022, shortlisting technology solutions to undergo further business case development and technical testing in the Alpha Phase, which kicked off in August 2022. The third and final phase (Beta Phase) will implement field testing of the technologies and will look to kick off in March 2023, subject to funding approval.
- The Discovery Phase - this was successfully conducted in early 2022, shortlisting technology solutions.
- The Alpha Phase - in late 2022, the selected technology solutions underwent further business case development, technical testing, and selection in this phase.
- The Beta Phase - this phase was completed in 2024 and investigated three offshore wind farms on the GB network, using them as case studies to build technical confidence and workable business models to build commercial confidence in the solutions' ability to provide stability services to the GB onshore network.
- Stage 4 – This phase will kick off by April 2025 and will aim to continue to de-risk the INCENTIVe STATCOM solution while additionally following a first-of-a-kind demonstration on the Germany network.
Project end dates
June 2022 (Discovery Phase)
January 2023 (Alpha Phase)
January 2025 (Beta Phase)
April 2026 (Phase 4)
Project lead
SSE Networks Transmission
Project partners
SSE Networks Transmission, National Grid ESO, University of Strathclyde, The Carbon Trust, EnBW, Equinor, Ørsted, RWE, ScottishPower Renewables, Shell, SSE Renewables, TotalEnergies and Vattenfall, together with funding from Ofgem’s Strategic Innovation Fund.

Setup under
Offshore Wind Accelerator (OWA)
Contact

Robert Keast, Project Manager
robert.keast@carbontrust.com