The Offshore Wind Accelerator Fatigue Testing of Welded Structures in Air (OWA FaWS) project brought together stakeholders from across the industry; developers, steel producers, testing institutions and certification bodies. The project’s output provides a solid baseline for the establishment of fatigue curves that targets real-world loading conditions and weld details.
Project end date
March 2024
Project value
€1,218,000
Project lead
Orsted Wind Power A/S
Partners
Ørsted, Parkwind, RWE, Scottish Power Renewables, Shell, SSE, Vattenfall

Setup under
Offshore Wind Accelerator (OWA)
Contact